GSI @ OCT


Aim

  1. We are going to use silvio as target. Monoenergetic: 200/220 MeV/u. PMMA or poly for modeling... Transversal dimension?
  2. One arm: chamber + LYSO (charged particles flux + shape along z)
  3. Other arm: Baf + collimator+ CMOS ?

When?

Starting from 9-14 May. Setting of cave takes ~ 1 day. We are going to have 1-2 shifts.

  • We start the 10th of May
  • We end the 15th May

Tentative schedule

  1. To be done.

Where

Cave A.

Before 10 setting of the cave + quality check of the beam.

Mechanics

Rec with wheels. (dismounting)

Table + arms to hold detectors.

  1. One start counter BEFORE the phantom.
  2. One arm should move in theta: New BM + LYso
  3. One arm is fixed @ 90 degrees (collimator, BaF, veto)
Target
  1. 5x5x20 PMMA
  2. 20x20x20 PMMA
  3. Testa (silvio)

Hardware

Gas system

Already @ GSI

  • Gas system.
  • Gas bottle (premixed 82/18 Ar Co2)
Chambers fluxed in series.

Detectors

To be brought from roma1.

  • New Chmb
  • 1 (or 2) BaF scintillators
  • Collimator?
  • Veto?
Detectors @ GSI.
  • Start counter (GSI)
To be brought from Roma1

  • New Start Counter read with two H10580 PMT, SC thickness: plexiglass 1,8 mm :: Aluminum foil 0,05 mm :: Black tape 0,25 mm
  • Lyso

Power supply

Already @ GSI

  • LV power supply: 4 channels. (for the two chambers)
To be brought from Roma1
  • HV: any other needed channel.
  • HV: 4 channels. [3 channels for the two chambers.]
Channels:
  • HV:
    • 3chs (New and OLd chmb)
    • 2chs (BaF)
    • 2chs HV
    • 1ch Start Counter GSI
    • 1ch veto
  • LV:
    • 4 channels (2 chambers)
    • 2 channels (Daisy)

Electronics

Already @ GSI

  • Crate Nim (ex FIRST trigger)
  • Crate VME
  • Scope (?)
  • Crate Camac (?)
To be brought from Roma1
  • Crate Camac
  • Crate Nim
NIM Modules
  • Most of them are @ GSI: nim/ecl translators, discriminators....
  • Nim/TTL translator (GSI)
VME Modules
  • 3 QDC modules: 2 Roma1, 1 GSI
  • 2 TDC modules: 1190 + ? KLOE TDCs? GSI TDC?
  • I/O
  • Scaler
Delay modules?

Cables

  • 40 Lemo Cables (GSI)

DAQ

  • Bridged ACQ.

ELOG

The elog of the TB can be found here

Software

Acquisition

Being developed on workstation2. Project will be under svn.

svn co svn+ssh://<youraccount>@pcaen1.ing2.uniroma1.it/home/sarti/SvnRepos/TestBeamCode/GsiMay_2012_Bridge

Decoding

Being developed on workstation2. Project will be under svn.

svn co svn+ssh://<youraccount>@pcaen1.ing2.uniroma1.it/home/sarti/SvnRepos/TestBeamCode/GsiMay_2012_BridgeDecode

Configuration

QDC

TDC

Strategy

Calibration of detectors

  • Lyso: should we calibrate?

Neutral Analysis

Code is in svn (BridgeDecode folder)

  • Ana.cc (to be compiled with makefile_Ana)
  • Full production can be launched with SingleMeasurements.sh
  • The output has to be proceessed with macros in folder Spettro/

Several test done

  • PhotonsOutput: contains "benchmark results" from Michi
  • PhotonsOutputNew: New calibration + added DT correction INSIDE Ana.cc + removal of scorsize == 1 requirement
  • PhotonsOutputNewNoSele: removed the "single carbon" selection + New calibration + added DT correction INSIDE Ana.cc + removal of scorsize == 1 requirement
  • PhotonsOutputNewNoSele_AndTiming: removed the "single carbon" selection + New calibration + added DT correction INSIDE Ana.cc + removal of scorsize == 1 requirement .. Now to compute the time we use the AND and not the OR (shouldn't make any real difference)

-- AlessioSarti - 2012-03-06

Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions
Topic revision: r4 - 2013-05-23 - AlessioSarti
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback